Friday, February 3, 2012

I am writing this at 4:00am. Still jet-lagged.

This week we finished electric and indoor plumbing. JouLee has finished the outdoor sink so Dennis and I can start the tile next week. The gutters for both dorms will be installed next week.
As slow as things seem, we have only been on-site for a week.

Trying to get ready to go from 11 students to 40 students. Need four time as many beds, chairs, dishes, everything. I hope Ajan and handle this many kids. My main concern is that they need another person to help with the spiritual needs of the students.